PSPO-I · Question #1
When should the Product Owner update the project plan? (choose the best answer)
The correct answer is B. The Product Backlog is the plan in Scrum. It is updated as new information and insights emerge. The Product Owner is responsible for managing and refining the Product Backlog, which is the single source of truth for the plan of the product development. The Product Backlog is a living artifact that changes as the product and the market evolve. The Product Owner updates the…
Question
When should the Product Owner update the project plan? (choose the best answer)
Options
- ABefore the Sprint Planning to know how much work will have to be done in the Sprint.
- BThe Product Backlog is the plan in Scrum. It is updated as new information and insights emerge.
- CAfter the Daily Scrum to ensure an accurate daily overview of project progress.
- DThe project plan must be updated prior to the Sprint Retrospective.
How the community answered
(52 responses)- A6% (3)
- B88% (46)
- C2% (1)
- D4% (2)
Explanation
The Product Owner is responsible for managing and refining the Product Backlog, which is the single source of truth for the plan of the product development. The Product Backlog is a living artifact that changes as the product and the market evolve. The Product Owner updates the Product Backlog continuously based on feedback, learning, and stakeholder needs. There is no separate project plan document in Scrum. [Scrum Guide], section 3.1: "The Product Backlog is an emergent, ordered list of what is needed to improve the product." [Professional Scrum Product Owner], chapter 5: "The Product Backlog represents everything necessary to develop and launch a successful product." [What is a Product Backlog?]: "The Product Backlog is a list of all things that need to be done within