PSM-I · Question #86

What is the result of the Sprint Review?

The correct answer is D. A revised Product Backlog that defines the probable Product Backlog items for the next Sprint. The key output of a Sprint Review is a revised Product Backlog. During the Sprint Review, the Scrum Team and stakeholders collaboratively inspect the Increment and adapt the Product Backlog based on feedback and new insights - defining probable items for upcoming Sprints. Option

Submitted by kevin_r· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

What is the result of the Sprint Review?

Options

  • ACommon understanding of progress toward the Sprint Goal and how progress is trending toward
  • BCommon understanding of what can be delivered in the Increment and how will the work needed
  • CA list of improvements that the Scrum Team will implement in the next Sprint
  • DA revised Product Backlog that defines the probable Product Backlog items for the next Sprint

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    7% (2)
  • D
    90% (27)

Explanation

The key output of a Sprint Review is a revised Product Backlog. During the Sprint Review, the Scrum Team and stakeholders collaboratively inspect the Increment and adapt the Product Backlog based on feedback and new insights - defining probable items for upcoming Sprints. Option A describes the purpose of the Daily Scrum (tracking progress toward the Sprint Goal). Option B describes what happens during Sprint Planning (deciding what can be delivered). Option C describes the output of the Sprint Retrospective (process improvement actions), not the Sprint Review.

Topics

#Sprint Review#Scrum Events#Product Backlog#Scrum Framework