PSM-I · Question #85

Who is responsible for crafting the Sprint Goal at the Sprint Planning?

The correct answer is C. The Scrum Team. The Sprint Goal is crafted collaboratively by the entire Scrum Team during Sprint Planning. The Product Owner proposes an objective based on the Product Backlog, and the Development Team negotiates what can be achieved. The resulting Sprint Goal is a shared commitment by the…

Submitted by ngozi_ng· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

Who is responsible for crafting the Sprint Goal at the Sprint Planning?

Options

  • AThe Key Stakeholders
  • BThe Scrum Master
  • CThe Scrum Team
  • DThe Development Team
  • EThe Product Owner

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    5% (2)
  • C
    86% (32)
  • E
    3% (1)

Explanation

The Sprint Goal is crafted collaboratively by the entire Scrum Team during Sprint Planning. The Product Owner proposes an objective based on the Product Backlog, and the Development Team negotiates what can be achieved. The resulting Sprint Goal is a shared commitment by the whole Scrum Team - not solely the Product Owner's directive or the Development Team's own plan. Collaboration between all three roles is essential.

Topics

#Sprint Planning#Sprint Goal#Scrum Team Responsibilities#Scrum Events

Community Discussion

No community discussion yet for this question.