PSM-I · Question #41
Choose two responsibilities of a self-organizing Development Team. (Choose two.)
The correct answer is B. Pull Product Backlog items for the Sprint. C. Do the work planned in the Sprint Backlog. A self-organizing Development Team is responsible for (B) pulling Product Backlog items into the Sprint during Sprint Planning - they decide how much work they can take on - and (C) doing the actual work planned in the Sprint Backlog to create the Increment. These reflect the…
Question
Choose two responsibilities of a self-organizing Development Team. (Choose two.)
Options
- AReorder the Product Backlog.
- BPull Product Backlog items for the Sprint.
- CDo the work planned in the Sprint Backlog.
- DIncrease velocity.
- EReport daily progress to stakeholders.
How the community answered
(49 responses)- A2% (1)
- B88% (43)
- D6% (3)
- E4% (2)
Explanation
A self-organizing Development Team is responsible for (B) pulling Product Backlog items into the Sprint during Sprint Planning - they decide how much work they can take on - and (C) doing the actual work planned in the Sprint Backlog to create the Increment. These reflect the team's autonomy and accountability for execution. (A) Reordering the Product Backlog is the Product Owner's sole responsibility. (D) Increasing velocity is not a Scrum responsibility; velocity is a byproduct, not a mandated goal. (E) The Daily Scrum is an internal team synchronization event, not a stakeholder reporting mechanism.
Topics