PSM-I · Question #40
When is implementation of a Product Backlog item considered complete?
The correct answer is B. When the item has no work remaining in order to be potentially released. A Product Backlog item is complete when it has no remaining work needed to be potentially released (B)-this is the essence of the Definition of Done. 'Potentially releasable' is a key Scrum concept: the increment must be in a usable state regardless of whether the Product Owner…
Question
When is implementation of a Product Backlog item considered complete?
Options
- AAt the end of the Sprint.
- BWhen the item has no work remaining in order to be potentially released.
- CWhen QA reports that the item passes all acceptance criteria.
- DWhen all work in the Sprint Backlog related to the item is finished.
How the community answered
(48 responses)- A2% (1)
- B92% (44)
- C2% (1)
- D4% (2)
Explanation
A Product Backlog item is complete when it has no remaining work needed to be potentially released (B)-this is the essence of the Definition of Done. 'Potentially releasable' is a key Scrum concept: the increment must be in a usable state regardless of whether the Product Owner chooses to release it. End of Sprint (A) is a time boundary, not a quality gate. QA sign-off on acceptance criteria (C) may be part of Done but isn't the full definition-Done includes all quality, documentation, and integration requirements. Finishing Sprint Backlog tasks (D) is necessary but not sufficient; the item must meet the full Definition of Done.
Topics
Community Discussion
No community discussion yet for this question.