PSM-I · Question #31

Which statement best describes the Sprint Review?

The correct answer is D. It is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what. The Sprint Review is a collaborative working session where the Scrum Team and stakeholders inspect the Sprint's outcome and adapt the Product Backlog accordingly (D). It is forward-looking and focused on maximizing value. Option A incorrectly frames it as punitive - Scrum does…

Submitted by lukas.cz· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

Which statement best describes the Sprint Review?

Options

  • AIt is used to congratulate the Development Team if it did what it forecast, or to punish the
  • BIt is a demo at the end of the Sprint for everyone in the organization to check on the work done.
  • CIt is a mechanism to control the Development Team's activities during a Sprint.
  • DIt is when the Scrum Team and stakeholders inspect the outcome of a Sprint and figure out what

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    5% (2)
  • D
    90% (35)

Explanation

The Sprint Review is a collaborative working session where the Scrum Team and stakeholders inspect the Sprint's outcome and adapt the Product Backlog accordingly (D). It is forward-looking and focused on maximizing value. Option A incorrectly frames it as punitive - Scrum does not operate on reward/punishment. Option B is too broad; it is not an open organizational showcase. Option C contradicts Scrum's principle of team self-organization - the Sprint Review is not a control mechanism.

Topics

#Sprint Review#Scrum Events#Inspection and Adaptation#Stakeholder Collaboration

Community Discussion

No community discussion yet for this question.