The correct answer is B: False. The correct answer is B, because the Product Owner does not make sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders. The Scrum Guide states that "the number of items selected from the Product Backlog for the Sprint is solely up to the D
Question
The Product Owner makes sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders.
Options
- ATrue
- BFalse
Explanation
The correct answer is B, because the Product Owner does not make sure the team selects enough from the Product Backlog for a Sprint to satisfy the stakeholders. The Scrum Guide states that "the number of items selected from the Product Backlog for the Sprint is solely up to the Development Team. Only the Development Team can assess what it can accomplish over the upcoming Sprint." Therefore, the Development Team is responsible for choosing the scope of work for a Sprint.
Topics
Community Discussion
No community discussion yet for this question.