The correct answer is C: Work remaining across time.. The correct answer is C, because if burndown charts are used to visualize progress, they track work remaining across time. A burndown chart is a graphical representation of the amount of work left to do versus the time available. It helps the Scrum Team monitor and forecast the p
Question
If burndown charts are used to visualize progress, what do they track?
Options
- AAccumulated cost.
- BIndividual worker productivity.
- CWork remaining across time.
- DAccumulated business value delivered to the customer.
Explanation
The correct answer is C, because if burndown charts are used to visualize progress, they track work remaining across time. A burndown chart is a graphical representation of the amount of work left to do versus the time available. It helps the Scrum Team monitor and forecast the progress toward the Sprint Goal.
Topics
Community Discussion
No community discussion yet for this question.