A product Increment must be released to production at the end of each Sprint.
The correct answer is B. False. This is a common misconception. The Increment must be in a 'Done', potentially releasable state at the end of every Sprint - but the decision to actually release it belongs to the Product Owner. The Product Owner may choose to release it, hold it, or combine it with future…
Question
A product Increment must be released to production at the end of each Sprint.
Options
- ATrue
- BFalse
How the community answered
(33 responses)- A12% (4)
- B88% (29)
Explanation
This is a common misconception. The Increment must be in a 'Done', potentially releasable state at the end of every Sprint - but the decision to actually release it belongs to the Product Owner. The Product Owner may choose to release it, hold it, or combine it with future Increments before releasing. Scrum requires that the Increment is always in a deployable condition, but it does not require that deployment actually happens every Sprint.
Topics
Community Discussion
No community discussion yet for this question.