Question
A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items "Done" by the end of the Sprint. Which three phrases best describe the purpose of a definition of "Done"? (Choose three.)
Options
- AIt controls whether the developers have performed their tasks.
- BIt provides a template for elements that need to be included in the technical documentation.
- CIt creates transparency over the work inspected at the Sprint Review.
- DIt trucks the percent completeness of a Product Backlog item.
- EIt guides the Development Team is creating a forecast at the Sprint Planning.
- FIt defines what it takes for an Increment to be ready for release.