PSM-I · Question #157
Who participates in the Sprint Planning? Select three.
The correct answer is B. The Product Owner C. The Development Team D. The Scrum Master. Sprint Planning involves the Product Owner (B), the Development Team (C), and the Scrum Master (D). The Product Owner presents the prioritized backlog and the Sprint Goal candidate. The Development Team selects work and creates the Sprint Backlog. The Scrum Master facilitates…
Question
Who participates in the Sprint Planning? Select three.
Options
- AThe Team Manager
- BThe Product Owner
- CThe Development Team
- DThe Scrum Master
- EThe Key Stakeholders
How the community answered
(41 responses)- A5% (2)
- B93% (38)
- E2% (1)
Explanation
Sprint Planning involves the Product Owner (B), the Development Team (C), and the Scrum Master (D). The Product Owner presents the prioritized backlog and the Sprint Goal candidate. The Development Team selects work and creates the Sprint Backlog. The Scrum Master facilitates and ensures the event stays productive. The Team Manager (A) is not a Scrum role and has no place in this event. Key Stakeholders (E) are not participants in Sprint Planning - they engage primarily during the Sprint Review.
Topics
Community Discussion
No community discussion yet for this question.