PSM-I · Question #156
PSM-I Question #156: Real Exam Question with Answer & Explanation
The correct answer is B: Estimates are made by the Development Team.. The correct answer is B, because the guideline that a Scrum Master should give is that estimates are made by the Development Team. The Scrum Guide states that "the number of items selected from the Product Backlog for the Sprint is solely up to the Development Team. Only the Deve
Question
A Product Owner wants advice from the Scrum Master about estimating work in Scrum. Which of these is the guideline that a Scrum Master should give?
Options
- AProduct Backlog items must be estimated in story points.
- BEstimates are made by the Development Team.
- CEstimates must be in relative units.
- DScrum forbids estimating.
- EEstimates are made by the Product Owner, but are best checked with the Development Team.
Explanation
The correct answer is B, because the guideline that a Scrum Master should give is that estimates are made by the Development Team. The Scrum Guide states that "the number of items selected from the Product Backlog for the Sprint is solely up to the Development Team. Only the Development Team can assess what it can accomplish over the upcoming Sprint." Therefore, the Development Team should estimate the work in Scrum, using any method or unit they prefer.
Topics
Community Discussion
No community discussion yet for this question.