PSM-I · Question #126

What happens during the Sprint? Select three answers.

The correct answer is A. Scope may be clarified and re-negotiated between the Product Owner and Development Team as B. Quality goals do not decrease C. No changes are made that would endanger the Sprint Goal. The Scrum Guide defines three key rules for the Sprint: (A) Scope may be clarified and re-negotiated between the Product Owner and Development Team as more is learned - this allows adaptation without abandoning the Sprint Goal; (B) Quality goals do not decrease - the Definition o

Submitted by tyler.j· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

What happens during the Sprint? Select three answers.

Options

  • AScope may be clarified and re-negotiated between the Product Owner and Development Team as
  • BQuality goals do not decrease
  • CNo changes are made that would endanger the Sprint Goal
  • DSprint scope is defined at the Sprint Planning and cannot be changed
  • EThe Sprint Goal is changed frequently to reflect the status of the remaining work

How the community answered

(32 responses)
  • A
    94% (30)
  • D
    3% (1)
  • E
    3% (1)

Explanation

The Scrum Guide defines three key rules for the Sprint: (A) Scope may be clarified and re-negotiated between the Product Owner and Development Team as more is learned - this allows adaptation without abandoning the Sprint Goal; (B) Quality goals do not decrease - the Definition of Done ensures consistent quality standards are never compromised; and (C) No changes are made that would endanger the Sprint Goal - the Sprint Goal is the one stable commitment throughout the Sprint. Option D is incorrect because scope can be renegotiated (just not in ways that endanger the Sprint Goal). Option E is incorrect because the Sprint Goal is fixed once the Sprint begins and should not change.

Topics

#Sprint#Sprint Goal#Scope Negotiation#Quality