What part of the capacity of the Development Team does Product Backlog refinement usually consume?

The correct answer is A. Not more than 10%. According to the Scrum Guide, Product Backlog refinement usually consumes no more than 10% of the capacity of the Development Team. This activity includes adding detail, estimates, and order to Product Backlog items. It is an ongoing process, not a formal Scrum event, and the…

Submitted by jaden.t· Apr 18, 2026Understanding and Applying the Scrum Framework

Question

What part of the capacity of the Development Team does Product Backlog refinement usually consume?

Options

  • ANot more than 10%
  • BNot more than 20%
  • CNot more than 5%
  • DThe Development Team is not authorized for Product Backlog refinement

How the community answered

(47 responses)
  • A
    87% (41)
  • B
    6% (3)
  • C
    2% (1)
  • D
    4% (2)

Explanation

According to the Scrum Guide, Product Backlog refinement usually consumes no more than 10% of the capacity of the Development Team. This activity includes adding detail, estimates, and order to Product Backlog items. It is an ongoing process, not a formal Scrum event, and the Development Team performs this work in collaboration with the Product Owner. The 10% cap ensures that refinement doesn't crowd out actual development work during the Sprint.

Topics

#Product Backlog Refinement#Development Team Capacity#Scrum Guide#Scrum Activities