PSD · Question #116

Which of the following best describes an increment of working software?

The correct answer is A. Additions features in a usable state that complement those delivered in previous iterations. An increment is the usable value added in the last sprint plus the usable work of all previous

Developing Products

Question

Which of the following best describes an increment of working software?

Options

  • AAdditions features in a usable state that complement those delivered in previous iterations
  • BUML diagrams that describe how to deliver functionality in future iterations
  • CA new user interface design for functionality delivered in previous iterations
  • DAn automated test suite to verify functionality delivered in previous iterations
  • EA decomposition of all product backlog items into tasks for future sprint backlog lists

How the community answered

(28 responses)
  • A
    93% (26)
  • B
    4% (1)
  • E
    4% (1)

Explanation

An increment is the usable value added in the last sprint plus the usable work of all previous

Topics

#increment#working software#done#iterative delivery