Which is a responsibility of the project board?

The correct answer is C. To ensure effective communication with external stakeholders. See the full explanation below for the reasoning.

Question

Which is a responsibility of the project board?

Options

  • ATo manage the team managers and project support
  • BTo ensure production of the project's outputs
  • CTo ensure effective communication with external stakeholders
  • DTo implement the change control approach

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    12% (4)
  • C
    79% (26)
  • D
    6% (2)