The correct answer is C. Corporate, program management or the customer. See the full explanation below for the reasoning.
Question
Which role is responsible for appointing the senior user in a project that is independent from a program?
Options
- AThe project manager
- BThe executive
- CCorporate, program management or the customer
- DProject assurance