nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #98

When examining a project issue, which three aspects should be considered? 1 Performance targets 2 Business Case 3 Resources 4 Risk

The correct answer is C. 1 2 4. See the full explanation below for the reasoning.

Question

When examining a project issue, which three aspects should be considered? 1 Performance targets 2 Business Case 3 Resources 4 Risk

Options

  • A1 3 4
  • B2 3 4
  • C1 2 4
  • D1 2 3

How the community answered

(28 responses)
  • A
    11% (3)
  • B
    4% (1)
  • C
    79% (22)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.