Which is a minimum requirement for applying the risk theme?

The correct answer is A. Threats must be assessed for their impact on the viability of the project. See the full explanation below for the reasoning.

Question

Which is a minimum requirement for applying the risk theme?

Options

  • AThreats must be assessed for their impact on the viability of the project
  • BA single role that is responsible for all risks must be defined
  • CThe PRINCE2 risk management procedure must be followed
  • DTeam managers must maintain their own risk registers

How the community answered

(23 responses)
  • A
    83% (19)
  • C
    4% (1)
  • D
    13% (3)

Community Discussion

No community discussion yet for this question.