PeopleCert
PRINCE2-FOUNDATION · Question #969
Identify the missing words in the following sentence. The project manager [ ? ] for day-to-day management of the project.
The correct answer is C. has responsibility. See the full explanation below for the reasoning.
Question
Identify the missing words in the following sentence. The project manager [ ? ] for day-to-day management of the project.
Options
- Aand the project board are responsible
- Band the team manager(s) are accountable
- Chas responsibility
- Ddecides who is responsible
How the community answered
(27 responses)- A4% (1)
- B15% (4)
- C70% (19)
- D11% (3)
Community Discussion
No community discussion yet for this question.