PRINCE2-FOUNDATION · Question #969

PRINCE2-FOUNDATION Question #969: Real Exam Question with Answer & Explanation

The correct answer is C. has responsibility. See the full explanation below for the reasoning.

Question

Identify the missing words in the following sentence. The project manager [ ? ] for day-to-day management of the project.

Options

  • Aand the project board are responsible
  • Band the team manager(s) are accountable
  • Chas responsibility
  • Ddecides who is responsible