PeopleCert
PRINCE2-FOUNDATION · Question #966
PRINCE2-FOUNDATION Question #966: Real Exam Question with Answer & Explanation
The correct answer is D. Managing product delivery. See the full explanation below for the reasoning.
Question
Which process monitors work that has been assigned to a team manager?
Options
- AControlling a stage
- BDirecting a project
- CManaging a stage boundary
- DManaging product delivery
Community Discussion
No community discussion yet for this question.