Where should decisions regarding the tailoring of the project be recorded?

The correct answer is D. Stage plan. See the full explanation below for the reasoning.

Question

Where should decisions regarding the tailoring of the project be recorded?

Options

  • AProject brief
  • BProject initiation documentation
  • CProject mandate
  • DStage plan

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    4% (2)
  • C
    10% (5)
  • D
    82% (42)