Question

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

Options

  • AAppointing the project board and producing the project brief
  • BPlanning the initiation stage and appointing the project manager
  • CProducing the additional role descriptions and validating the project product description
  • DVerifying the project approach and capturing previous lessons