If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

The correct answer is A. Appointing the project board and producing the project brief. See the full explanation below for the reasoning.

Question

If a project is part of a programme, which 'starting up a project' process activities are MOST likely to be reduced or eliminated?

Options

  • AAppointing the project board and producing the project brief
  • BPlanning the initiation stage and appointing the project manager
  • CProducing the additional role descriptions and validating the project product description
  • DVerifying the project approach and capturing previous lessons

How the community answered

(21 responses)
  • A
    76% (16)
  • B
    5% (1)
  • C
    5% (1)
  • D
    14% (3)