PRINCE2-FOUNDATION · Question #902

Which level of management sets the project level tolerances?

The correct answer is D. Project manager. See the full explanation below for the reasoning.

Question

Which level of management sets the project level tolerances?

Options

  • AProject board
  • BTeam manager
  • CCorporate, programme management or the customer
  • DProject manager

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    12% (3)
  • D
    81% (21)