PeopleCert
PRINCE2-FOUNDATION · Question #902
Which level of management sets the project level tolerances?
The correct answer is D. Project manager. See the full explanation below for the reasoning.
Question
Which level of management sets the project level tolerances?
Options
- AProject board
- BTeam manager
- CCorporate, programme management or the customer
- DProject manager
How the community answered
(26 responses)- A4% (1)
- B4% (1)
- C12% (3)
- D81% (21)
Community Discussion
No community discussion yet for this question.