How is the tailoring approach defined for a project?

The correct answer is A. The project board approves the approach. See the full explanation below for the reasoning.

Question

How is the tailoring approach defined for a project?

Options

  • AThe project board approves the approach
  • BThe project board documents the approach
  • CProject assurance approves the approach
  • DProject assurance documents the approach

How the community answered

(60 responses)
  • A
    78% (47)
  • B
    12% (7)
  • C
    7% (4)
  • D
    3% (2)

Community Discussion

No community discussion yet for this question.