How is the tailoring approach defined for a project?
The correct answer is A. The project board approves the approach. See the full explanation below for the reasoning.
Question
How is the tailoring approach defined for a project?
Options
- AThe project board approves the approach
- BThe project board documents the approach
- CProject assurance approves the approach
- DProject assurance documents the approach
How the community answered
(60 responses)- A78% (47)
- B12% (7)
- C7% (4)
- D3% (2)