PRINCE2-FOUNDATION · Question #860
Which describes a risk event?
The correct answer is A. The area of uncertainty in terms of the threat or opportunity. See the full explanation below for the reasoning.
Question
Which describes a risk event?
Options
- AThe area of uncertainty in terms of the threat or opportunity
- BThe derivation or sources of a potential risk to the project
- CThe achievement of a milestone on the Project Plan
- DThe sequence of events and actions that will be put in place if a risk occurs
How the community answered
(53 responses)- A75% (40)
- B8% (4)
- C4% (2)
- D13% (7)