Question
Which describes a risk event?
Options
- AThe area of uncertainty in terms of the threat or opportunity
- BThe derivation or sources of a potential risk to the project
- CThe achievement of a milestone on the Project Plan
- DThe sequence of events and actions that will be put in place if a risk occurs