Which describes risk probability?

The correct answer is D. A measure of the likelihood of the risk occurring. See the full explanation below for the reasoning.

Question

Which describes risk probability?

Options

  • ALevel of risks which the project can tolerate before escalating to the Project Board
  • BProbable effect on the project delivering its objectives
  • CTimeframe within which the risk may occur
  • DA measure of the likelihood of the risk occurring

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    4% (1)
  • C
    13% (3)
  • D
    74% (17)