Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and…
The correct answer is B. project budget. See the full explanation below for the reasoning.
Question
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.
Options
- Achange budget
- Bproject budget
- Cproject's cost tolerance
- Dproject's risk tolerance
How the community answered
(17 responses)- A6% (1)
- B76% (13)
- C6% (1)
- D12% (2)
Community Discussion