Which is NOT considered when defining risk tolerance?

The correct answer is B. The allocated risk budget. See the full explanation below for the reasoning.

Question

Which is NOT considered when defining risk tolerance?

Options

  • AA Project Board's attitude towards risk taking
  • BThe allocated risk budget
  • CAn organization's risk appetite
  • DThe amount of risk a Project Board considers acceptable

How the community answered

(32 responses)
  • A
    3% (1)
  • B
    84% (27)
  • C
    9% (3)
  • D
    3% (1)