PRINCE2-FOUNDATION · Question #845

PRINCE2-FOUNDATION Question #845: Real Exam Question with Answer & Explanation

Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #845. The question stem and answer options stay visible for context.

Question

Which statement defines a risk?

Options

  • AA certain event occurring in the future that will have a negative impact on the project's objectives
  • BAn event that has already occurred that the Project Manager must deal with immediately
  • CAn uncertain event, or set of events that, should it or they occur, will have an effect on the
  • DAn uncertain event, or set of events that, should it or they occur, will be automatically escalated to