Which of the following statements about quality assurance and Project Assurance is true?
The correct answer is D. Project Assurance ensures compliance to standards within the project environment; quality. See the full explanation below for the reasoning.
Question
Which of the following statements about quality assurance and Project Assurance is true?
Options
- AProject Assurance is the responsibility of the corporate organization; quality assurance is the
- BProject Assurance is independent of the Project; quality assurance is only independent of the
- CProject Assurance may be delegated within a project; quality assurance must be undertaken by
- DProject Assurance ensures compliance to standards within the project environment; quality
How the community answered
(29 responses)- A14% (4)
- B7% (2)
- C7% (2)
- D72% (21)