nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #830

Which statement applies to Stage Plans?

The correct answer is C. Assist the Project Manager in the day-to-day running and control of the project. See the full explanation below for the reasoning.

Question

Which statement applies to Stage Plans?

Options

  • AAlways have the same duration as the Project Plan
  • BAre produced at the same time as the Project Initiation Documentation
  • CAssist the Project Manager in the day-to-day running and control of the project
  • DProvide a baseline against which the Project Board monitor overall progress

How the community answered

(33 responses)
  • A
    9% (3)
  • B
    15% (5)
  • C
    73% (24)
  • D
    3% (1)

Community Discussion