Whose approval is needed to replace a Stage Plan with an Exception Plan?

The correct answer is B. Project Board. See the full explanation below for the reasoning.

Question

Whose approval is needed to replace a Stage Plan with an Exception Plan?

Options

  • ACorporate or programme management
  • BProject Board
  • CProject Manager
  • DTeam Manager

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    81% (25)
  • C
    6% (2)
  • D
    10% (3)