Whose approval is needed to replace a Stage Plan with an Exception Plan?
The correct answer is B. Project Board. See the full explanation below for the reasoning.
Question
Whose approval is needed to replace a Stage Plan with an Exception Plan?
Options
- ACorporate or programme management
- BProject Board
- CProject Manager
- DTeam Manager
How the community answered
(31 responses)- A3% (1)
- B81% (25)
- C6% (2)
- D10% (3)