nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #804

PRINCE2-FOUNDATION Question #804: Real Exam Question with Answer & Explanation

Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #804. The question stem and answer options stay visible for context.

Question

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

Options

  • Aproject cost tolerance
  • Bstage cost tolerance
  • CWork Package cost tolerance
  • Dproduct cost tolerance

Unlock PRINCE2-FOUNDATION to see the answer