Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
The correct answer is C. Work Package cost tolerance. See the full explanation below for the reasoning.
Question
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
Options
- Aproject cost tolerance
- Bstage cost tolerance
- CWork Package cost tolerance
- Dproduct cost tolerance
How the community answered
(31 responses)- A6% (2)
- B3% (1)
- C71% (22)
- D19% (6)