PRINCE2-FOUNDATION · Question #796

Which is a benefit of using PRINCE2?

The correct answer is C. Can be applied to any type of project. See the full explanation below for the reasoning.

Question

Which is a benefit of using PRINCE2?

Options

  • AEnables the management of projects as well as of 'business as usual' activities
  • BCan be tailored by leaving out elements of the method for some projects
  • CCan be applied to any type of project
  • DAvoids the need to involve corporate or programme management

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    83% (24)
  • D
    10% (3)