PeopleCert
PRINCE2-FOUNDATION · Question #794
Which is NOT one of the PRINCE2 integrated elements?
The correct answer is C. The products. See the full explanation below for the reasoning.
Question
Which is NOT one of the PRINCE2 integrated elements?
Options
- ATailoring PRINCE2 to the project environment
- BThe processes
- CThe products
- DThe themes
How the community answered
(39 responses)- A5% (2)
- B10% (4)
- C79% (31)
- D5% (2)
Community Discussion