PRINCE2-FOUNDATION · Question #785
What product is used to maintain a record of those who have an interest in the project and their information requirements?
The correct answer is B. Communication Management Strategy. See the full explanation below for the reasoning.
Question
What product is used to maintain a record of those who have an interest in the project and their information requirements?
Options
- AProject Plan
- BCommunication Management Strategy
- CProject Brief
- DProject Product Description
How the community answered
(55 responses)- A11% (6)
- B78% (43)
- C4% (2)
- D7% (4)