PRINCE2-FOUNDATION · Question #778

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

The correct answer is C. Create user and supplier groups. See the full explanation below for the reasoning.

Question

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

Options

  • ACreate a separate Project Board to manage the supplier elements of the project
  • BCreate multiple smaller Project Boards during the process of Starting up a Project, one for each of
  • CCreate user and supplier groups
  • DAppoint corporate quality assurance to perform the Project Assurance role for all members of the

How the community answered

(36 responses)
  • A
    11% (4)
  • B
    6% (2)
  • C
    81% (29)
  • D
    3% (1)