PRINCE2-FOUNDATION · Question #775
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
The correct answer is C. Managing Product Delivery. See the full explanation below for the reasoning.
Question
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Options
- AClosing a Project
- BManaging a Stage Boundary
- CManaging Product Delivery
- DDirecting a Project
How the community answered
(46 responses)- A7% (3)
- B13% (6)
- C76% (35)
- D4% (2)