Which of the following statements about the Project Initiation Documentation are true? 1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board…

The correct answer is C. Both 1 and 2 are true. See the full explanation below for the reasoning.

Question

Which of the following statements about the Project Initiation Documentation are true? 1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project. 2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Options

  • AOnly 1 is true
  • BOnly 2 is true
  • CBoth 1 and 2 are true
  • DNeither 1 or 2 are true

How the community answered

(25 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    84% (21)
  • D
    4% (1)