PRINCE2-FOUNDATION · Question #762
Who should act as the communication channel between a project and corporate or programme management?
The correct answer is A. Project Board. See the full explanation below for the reasoning.
Question
Who should act as the communication channel between a project and corporate or programme management?
Options
- AProject Board
- BProject Assurance
- CProject Manager
- DProject Support
How the community answered
(46 responses)- A83% (38)
- B2% (1)
- C11% (5)
- D4% (2)