PRINCE2-FOUNDATION · Question #754
Which process is triggered towards the end of the final stage when all the assigned work has been completed?
The correct answer is C. Closing a Project. See the full explanation below for the reasoning.
Question
Which process is triggered towards the end of the final stage when all the assigned work has been completed?
Options
- AManaging a Stage Boundary
- BManaging Product Delivery
- CClosing a Project
- DControlling a Stage
How the community answered
(16 responses)- A6% (1)
- B6% (1)
- C75% (12)
- D13% (2)