Which of the following statements about the Closing a Project process are true? 1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work…

The correct answer is B. Only 2 is true. See the full explanation below for the reasoning.

Question

Which of the following statements about the Closing a Project process are true? 1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage. 2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

Options

  • AOnly 1 is true
  • BOnly 2 is true
  • CBoth 1 and 2 are true
  • DNeither 1 or 2 are true

How the community answered

(40 responses)
  • A
    13% (5)
  • B
    78% (31)
  • C
    8% (3)
  • D
    3% (1)