PRINCE2-FOUNDATION · Question #734

What is an off-specification?

The correct answer is C. A type of issue. See the full explanation below for the reasoning.

Question

What is an off-specification?

Options

  • AA new requirement
  • BA quality tolerance
  • CA type of issue
  • DA major risk

How the community answered

(47 responses)
  • A
    11% (5)
  • B
    4% (2)
  • C
    83% (39)
  • D
    2% (1)