Which product records any project outcomes perceived as negative by stakeholders?
The correct answer is A. Business Case. See the full explanation below for the reasoning.
Question
Which product records any project outcomes perceived as negative by stakeholders?
Options
- ABusiness Case
- BProject Plan
- CCommunication Management Strategy
- DProject Product Description
How the community answered
(38 responses)- A71% (27)
- B3% (1)
- C16% (6)
- D11% (4)