nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #729

Which product records any project outcomes perceived as negative by stakeholders?

The correct answer is A. Business Case. See the full explanation below for the reasoning.

Question

Which product records any project outcomes perceived as negative by stakeholders?

Options

  • ABusiness Case
  • BProject Plan
  • CCommunication Management Strategy
  • DProject Product Description

How the community answered

(38 responses)
  • A
    71% (27)
  • B
    3% (1)
  • C
    16% (6)
  • D
    11% (4)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice