Which of the following steps would involve the sending of information regarding project threats or opportunities to any external stakeholders?

The correct answer is B. Communicate. See the full explanation below for the reasoning.

Question

Which of the following steps would involve the sending of information regarding project threats or opportunities to any external stakeholders?

Options

  • AIdentify
  • BCommunicate
  • CImplement
  • DPlan

How the community answered

(29 responses)
  • A
    7% (2)
  • B
    76% (22)
  • C
    14% (4)
  • D
    3% (1)