PRINCE2-FOUNDATION · Question #720

Which of the following is NOT one of the five risk management procedure steps?

The correct answer is D. Register. See the full explanation below for the reasoning.

Question

Which of the following is NOT one of the five risk management procedure steps?

Options

  • AAssess
  • BIdentify
  • CPlan
  • DRegister

How the community answered

(44 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    11% (5)
  • D
    82% (36)