nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #708

PRINCE2-FOUNDATION Question #708: Real Exam Question with Answer & Explanation

The correct answer is D. A plan for how and when a measurement of the achievement of the project's benefits can. See the full explanation below for the reasoning.

Question

Which of the following is NOT established as part of the pre-project work?

Options

  • AA Plan for the work of initiation
  • BInformation on the various ways the project can be delivered
  • CA description of what the project is to deliver
  • DA plan for how and when a measurement of the achievement of the project's benefits can

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice
Which of the following is NOT established as part of the... | PRINCE2-FOUNDATION Q#708 Answer | NerdExam