PeopleCert
PRINCE2-FOUNDATION · Question #708
Which of the following is NOT established as part of the pre-project work?
The correct answer is D. A plan for how and when a measurement of the achievement of the project's benefits can. See the full explanation below for the reasoning.
Question
Which of the following is NOT established as part of the pre-project work?
Options
- AA Plan for the work of initiation
- BInformation on the various ways the project can be delivered
- CA description of what the project is to deliver
- DA plan for how and when a measurement of the achievement of the project's benefits can
How the community answered
(48 responses)- A13% (6)
- B6% (3)
- C2% (1)
- D79% (38)
Community Discussion
No community discussion yet for this question.