PRINCE2-FOUNDATION · Question #655

What process covers the acceptance and execution of project work by external suppliers?

The correct answer is A. Controlling a Stage. See the full explanation below for the reasoning.

Question

What process covers the acceptance and execution of project work by external suppliers?

Options

  • AControlling a Stage
  • BManaging a Stage Boundary
  • CManaging Product Delivery
  • DDirecting a Project

How the community answered

(39 responses)
  • A
    79% (31)
  • B
    13% (5)
  • C
    3% (1)
  • D
    5% (2)