PRINCE2-FOUNDATION · Question #648
Which of the following is funded from a change budget?
The correct answer is B. Request for change. See the full explanation below for the reasoning.
Question
Which of the following is funded from a change budget?
Options
- AFallback plan
- BRequest for change
- CAction to reduce a threat
- DChange Authority
How the community answered
(39 responses)- A8% (3)
- B72% (28)
- C15% (6)
- D5% (2)